News1829-01-2026, 15:12

Goripalya–Hosahalli Bridge Opens in West Bengaluru After Two-Year Delay

  • The Goripalya–Hosahalli railway bridge in west Bengaluru has finally opened, providing relief to commuters after nearly two years of delays.
  • The reconstruction project, initially estimated at Rs 6 crore, faced significant hurdles due to undocumented live electricity cables discovered during demolition.
  • Relaying nine new power lines and securing approvals from multiple agencies caused an eight-month delay, pushing the actual reconstruction to early 2024.
  • The project scope expanded to include approach roads, concrete stretches, kerb work, and streetlights, nearly doubling the cost to Rs 12 crore.
  • The bridge's opening restores a crucial road link, easing traffic and ending prolonged inconvenience for residents, students, and businesses in Goripalya, Hosahalli, and surrounding areas.

Why It Matters: The Goripalya–Hosahalli railway bridge in west Bengaluru is now open, ending two years of delays and commuter inconvenience.