Sion Flyover: Deadline Set for July 2026 Opening, Work Gains Pace

  • The Sion Flyover is nearing completion, with a deadline set for July 15, 2026, for its full opening to traffic.
  • Pedestrian facilities have been enhanced, including a new foot overbridge and one completed subway pedestrian path, with another to follow.
  • Work within railway limits, including the main railway line, access roads, and two underpasses, has commenced.
  • The western side's four-phase work is expected to conclude by May 31, followed by the demolition of the old bridge's southern part.
  • Abhijit Bangar, Additional Commissioner of Mumbai Municipal Corporation, is closely monitoring the project to ensure timely completion.

Why It Matters: Sion Flyover is on track for a July 2026 opening, promising improved traffic flow and pedestrian safety.