Jaipur's Jwala Mata Temple Road Incomplete After 4 Years, Devotees Face Challenges

Jaipur
N
News18•28-01-2026, 08:11
Jaipur's Jwala Mata Temple Road Incomplete After 4 Years, Devotees Face Challenges
- •A nearly two-kilometer road to Jwala Mata Temple in Jobner, Jaipur, remains incomplete for four years despite crores sanctioned.
- •Initial work began in March 2022 with 4.29 crore rupees sanctioned and a six-month deadline, but stalled after 70% completion.
- •A second phase in June 2024 saw an additional 3.60 crore rupees sanctioned, initiating work on drains and safety walls.
- •The project includes two parking areas for over 150 vehicles, aiming to ease traffic and provide convenience for devotees.
- •Completion of the road is expected to boost religious tourism, create local employment, and improve traffic management in Jobner.
Why It Matters: Despite significant investment, the Jwala Mata Temple road in Jobner remains unfinished, hindering devotee access and local development.
✦